Wastewater treatment
Pleasant Grove WWTP UV Disinfection Addition
City of Roseville · Roseville, CA
Scope of work
Construction and installation of an Ultraviolet (UV) disinfection channel at the Pleasant Grove Wastewater Treatment Plant. Upgraded three existing channels with new UV disinfection equipment. Electrical and instrumentation including variable frequency drives, reduced voltage soft starters, security equipment, and new transformer.
Contract milestones
- November 2023Commencement
- October 2024Original completion
- January 2025Substantial completion
Start a conversation
Planning a project like this for your agency? Bring us in early.
Work with Auburn
Building Northern California’s water future.
Agencies, engineers and developers: bring us in early on your next water or wastewater project. Subcontractors and suppliers: see our bid calendar.